BHR Capital Project (Jan/Feb '23 Forecast)

Building

  • The building envelope will be completed (Roofing will be on, doors will be hung and hardware in place). Building will be secure and dry.
  • Once all rough ins are complete (electrical, plumbing) sheetrock will be hung & interior fit-out will continue.
  • Metal roofing will be installed on the cabanas and year-round meeting space.
  • The main power feed from the existing transformer will be placed to the building.
  • Bath accessories and plumbing fixtures will be placed.
  • Lighting and HVAC controls placed.

Pool

  • The plumbing work around the pool perimeter is complete and has passed all inspections.
  • The piping will be backfilled with the stockpiled material.
  • The pump room equipment work will begin and should be complete by the end of Feb.
  • Tilling work to be completed.
  • Preparations for plaster work will be made (embeds, lighting, wiring, etc).